Report title: Operations Report
Crew #: 335
Position: Commander
Report prepared by: Dave Laude
Date: 29Apr2026
Sol: 10
Non-nominal systems: None
Notes on non-nominal systems: None
ROVERS
Spirit rover used:
Hours: 0
Beginning charge: N/A
Ending charge: N/A
Currently charging: Yes
Opportunity rover:
Hours: 0
Beginning charge: N/A
Ending charge: N/A
Currently charging: Yes
Curiosity rover used:
Hours: 0
Beginning charge: N/A
Ending charge: N/A
Currently charging: Yes
Perseverance rover used:
Hours: 0
Beginning charge: N/A
Ending charge: N/A
Currently charging: Yes
General notes on rovers: Some key switches may need lubricant, especially Opportunity.
Summary of Hab operations:
Water Use (see notes): 32.94 gal/d
Main tank level (remaining gallons, see notes): 156 gal
Main water tank pipe heater (ON or OFF): OFF
Main water tank heater (ON or OFF) OFF (was removed)
Toilet tank emptied (NO or YES): NO
Summary of internet: Connection was used for research, accessing, and working on homework, sending reports, video editing and listening to music.
Summary of suits and radios: EVA suit #7, the single piece suit, had a ventilation failure near the end of sim yesterday. The fan was found non-functional. Dave opened the back and immediately saw a thick red wire dangling near the battery. This was the + battery connection. There was no reason for this found and remains a mystery. The connection was remade and found to be sound. It appears that any force on the wire due to its position, weight and bending would apply force downward thus reinforcing the connection. Once reattached, there was no fan function so the lower access panel was opened to troubleshoot more and one switch terminal to the fan was loose. Not just the wire held by screw was loose, but also the switch lug was loose in its molded plastic. Wiggling that connection occasionally powered up the fan. A replacement switch was not found with the replacement parts. Please have Scott Davis advise. This suit is not needed now.
Summary of GreenHab operations: (use information from the GreenHab report)
Water use: 6 gallons
Heater (ON or OFF): Auto
Supplemental light (hours of operation): Auto
Harvest (name, weight in grams): 0g
Summary of ScienceDome operations: Used to film creative projects, drying clay and manipulating clay
Dual split (Heat or AC, On or Off or Automatic): Automatic
Summary of RAM operations: DVM and 2 screw drivers removed to troubleshoot EVA suit #7. Will replace tools soon.
Summary of any observatory issues: Not used.
Summary of health and safety issues: redacted.
Questions, concerns and requests to Mission Support: None