Operations Report – January 2nd

Report title: Operations Report
Crew #: 326
Position: Crew Engineer
Report prepared by: Iris Stevenson
Date: 02-01-2026
Sol: 5
Non-nominal systems:

  • RAM skylight
  • GreenHab water tank sensor

Notes on non-nominal systems:

  • RAM skylight leaking water into the RAM following rain over the past few days
  • GreenHab water tank sensor has been underreporting for several days but GreenHab officer has said she used at least 2 gallons in watering tank while the tank reported 0 gallons of usage today

ROVERS
Spirit rover used: NONFUNCTIONAL
Hours:
Beginning charge:
Ending charge:
Currently charging:
Opportunity rover used: NO
Hours:
Beginning charge:
Ending charge:
Currently charging: YES
Curiosity rover used: NO
Hours:
Beginning charge:
Ending charge:
Currently charging: YES
Perseverance rover used: NO
Hours:
Beginning charge:
Ending charge:
Currently charging: YES
General notes on rovers:

Summary of Hab operations:
Water Use: 50.04 gal
Main tank level: 267.4 gal
Main water tank pipe heater: ON
Main water tank heater: ON
Toilet tank emptied: YES
Summary of internet: Nominal
Summary of suits and radios:

  • Zip ties came loose on the back panel of one helmet, but were replaced by Crew Engineer

Summary of GreenHab operations:
Water use: 0 gallons reported, 2 gallons used in watering can
Heater: ON
Supplemental light: 2 hours, 1800-2000
Harvest: None
Summary of ScienceDome operations:
Dual split: Automatic
Summary of RAM operations:

  • Pliers, flathead screwdriver, and wire cutters used by Crew Engineer to replace zip ties in back panel of one EVA suit helmet

Summary of any observatory issues:
Summary of health and safety issues:
Questions, concerns and requests to Mission Support: