Report title: Operations Report
Crew #: 326
Position: Crew Engineer
Report prepared by: Iris Stevenson
Date: 01-01-2026
Sol: 4
Non-nominal systems:
Notes on non-nominal systems:
ROVERS
Spirit rover used: NONFUNCTIONAL
Hours:
Beginning charge:
Ending charge:
Currently charging:
Opportunity rover used: Not used
Hours:
Beginning charge:
Ending charge:
Currently charging: No
Curiosity rover used: Not used
Hours:
Beginning charge:
Ending charge:
Currently charging: No
Perseverance rover used: Not used
Hours:
Beginning charge:
Ending charge:
Currently charging: No
General notes on rovers:
Summary of Hab operations:
Water Use: 23.46 gal
Main tank level: 317.4 gal
Main water tank pipe heater: ON
Main water tank heater: ON
Toilet tank emptied: NO
Summary of internet: Nominal
Summary of suits and radios:
- Minor issues on channel 1 with one radio during EVA
Summary of GreenHab operations:
Water use: 1 gallon
Heater: ON
Supplemental light: 4 hours
Harvest: lettuce, 10.25g
Summary of ScienceDome operations:
- Crew Scientist tested the bricks he made for his research project using his own tools
Dual split: Automatic
Summary of RAM operations: None
Summary of any observatory issues:
Summary of health and safety issues:
Questions, concerns and requests to Mission Support:
- Request for rovers Curiosity, Perseverance, and Opportunity to be plugged in in preparation for Sol 5 EVAs